Below is a more detailed breakdown of how we develop your product from concept to mass production.
We finalize the product design direction based on:
Outcome: Final design is approved before prototyping.
We create a 3D prototype to confirm:
Purpose: Validate physical design before engineering development.
Timeline: ~10 days
Shipping (optional): ~7 days by air
We develop a working prototype to validate:
Purpose: Ensure the product works as intended.
Timeline: ~25–35 days
Shipping (optional): ~7 days by air
We build production molds based on approved design.
Timeline: ~35–45 days
We produce final production-grade samples:
Quantity: 2 pcs
Timeline: ~3–5 days
Shipping: ~7 days by air
Before full production:
Then proceed to mass production.
Pilot: ~15 days
Mass production: ~35 days